Norwegian Spirit
NCL, ALMACO Group Marseile, FRANCE
Scope of work :
Construction of two fully new Food Handling areas to deck 7 and deck 12. Deck 7 area of 180m2 and Deck 12 area of 380m2. Work including full demolition of existing areas, new steel bulkheads and steel outfitting, Electrical, Piping and whole area outfitting works. As well provide all Piping, Steel, Stainless steel custom made profiles and all Electrical materials from Prydwen side.
Manpower :
224 workers including on site management team
Duration :
January 2020 – February 2020